A state lawmaker from Boston is calling for more transparency from the MBTA.
The development comes following an NBC10 investigation, which reported a $7.9 million project to refurbish historic trolleys on the Mattapan High Speed Line was two years behind schedule.
WATCH ANYTIME FOR FREE
Stream NBC10 Boston news for free, 24/7, wherever you are. |
NBC10 discovered the stripped-down shells were still sitting in an Everett facility, nowhere near a return to service.
Lawmakers who approved funding for the upgrades said the MBTA had not communicated the delays, which the agency attributed to an extensive lead paint removal process along with the effects of the pandemic.
Get updates on what's happening in Boston to your inbox. Sign up for our News Headlines newsletter.
Sen. Nick Collins filed an amendment that would require the T to start providing quarterly updates on capital projects. The amendment passed in the Senate and will be part of current budget debate taking place on Beacon Hill.
“I was disappointed and surprised,” Collins said when he first saw the NBC10 report. “I was surprised we didn’t hear directly from the T, given the magnitude of the project and the significance with respect to the communities it serves.”
MBTA spokesman Joe Pesaturo said the agency is targeting the middle of June for a formal briefing with lawmakers who represent Mattapan, Milton and Dorchester on the status of the trolley project.
PHOTOS: Historic MBTA Trolleys Stripped Down in Warehouse
Pesaturo also said the MBTA keeps elected officials, stakeholders, advocates and riders updated on capital projects through multiple methods, including social media, online project pages and Fiscal Management Control Board meetings.
However, the page dedicated to the Mattapan line transformation does not reflect the two-year delay. When asked, Pesaturo also said it did not appear the topic had come up during a FCMB meeting.