By now, riders should be enjoying upgraded trolleys along the Mattapan Line.
However, the NBC10 Investigators have learned the MBTA will be missing another deadline for the $8 million that will eventually bring modern amenities to the historic 1940s-era trolleys.
WATCH ANYTIME FOR FREE
>Stream NBC10 Boston news for free, 24/7, wherever you are. |
“It’s definitely really frustrating because we know there are a lot of riders who depend on the Mattapan trolley,” said Jarred Johnson with the advocacy organization Transit Matters. “We need transparency and we need accountability.”
A quick look at the timeline we’ve been following:
Get updates on what's happening in Boston to your inbox. Sign up for our >News Headlines newsletter.
- When the upgrades were announced, the T estimated the first trolleys would be on the tracks in the summer of 2019.
- Two years later, our investigation discovered the stripped-down shells of two trolleys were still sitting in an Everett warehouse.
- Following that report, the MBTA gave a date of August for the first rebuilt car.
- In October, we followed up again and found a trolley nowhere near ready to carry passengers.
- The transit agency pegged the end of 2021 as the deadline when riders would finally see the refurbished trolleys.
But it turns out the goalposts are moving once again.
To make proper adjustments for accelerating and braking, MBTA spokesman Joe Pesaturo said, the T is continuing to work with the vendor of the propulsion systems.
If the car performs as expected during the subsequent testing phase, it could go into service in January 2022, Pesaturo said. A timeline is still being established for the second refurbished trolley.
“The MBTA is grateful for the patience of Mattapan Line riders, as personnel work to ensure the rebuilt cars perform in a safe and reliable manner,” Pesaturo wrote in a statement.
The T previously attributed delays to an extensive lead paint-removal process and manpower issues during COVID.
Johnson, the executive director of Transit Matters, pointed out the upgrades are the just the first phase of a much larger project planned for the transit-dependent corridor. The results so far aren’t doing much to instill confidence.
“Obviously, riders are going to be disappointed anytime a deadline slips,” Johnson said. “But there needs to be more clarity about what some of those issues are.”
State lawmakers who represent communities served by the Mattapan Line also reacted to news of the latest delay.
“There needs to be meaningful progress here and it continues to be elusive,” said Rep. Bill Driscoll, who called for a meeting with T officials after our investigation earlier this year. “We’ve been told all the parts were available, the effort was redoubled to get this done, and yet here we are on Dec. 22. No refurbished cars are in service and no one can say with certainly when they will be.”
Rep. Brandy Fluker Oakley raised equity issues with the delayed project and pointed to recent service cuts to the Mattapan Line due to a shortage of drivers.
"I am frustrated and disheartened that this refurbishment process has been riddled with consistent delays and excuses,” Fluker Oakley said. “My community feels undervalued by the MBTA, and every missed deadline further erodes public trust.”
Ryan Kath can be reached at ryan.kath@nbcuni.com. You can follow him on Twitter or connect on Facebook.